Panjang = 1.260 meter
Ketebalan = 10 ~ 15 cm
Volume = 252.25 m3

1. UPAH

Pekerja = 0.357 Oh x 77.318.18 = 27.587.30
Tukang = 0.00 Oh x 96.095.00 = 0.00
Kepala Tukang = 0.025 Oh x 95.400.00 = 2.420.63
Mandor/Kepala Kelompok = 0.012 Oh x 84.100.00 = 1.000.00
JUMLAH (I) = 31.007.94
II. BAHAN
Semen = 0.315 Zak x 57.436.00 = 18.063.49
Pasir Pasang = 0.0611 m3 x 162.500.00 = 9.920.63
Pasir Urug = 0.0248 m3 x 162.500.00 = 4.023.81
Kerikil = 0.0402 m3x 110.455.00 = 4.444.44
JUMLAH (II) = 67.460.32
REKAP KEBUTUHAN BIAYA
Kebutuhan Upah (I) 31.007.94 x 1.260 m = 39.070.000
Kebutuhan bahan(II) 36.452.38 x 1.260 m = 45.930.000
Batu Mangga 4.00 M3 x 124.000 = 496.000
Papan Deletasi 30 Lbrx 77.318 = 2.319.540
Balok 5 x 5 8 lbr x 68.000= 544.000
Kereta Sorong 1 Unit x 446.000 = 446.000
Paku = 2.00 Kg x 13.255 = 26.510
Raskam = 2 bh x 8.920 = 17.840
Timba = 4 bh x 6.690 = 26.760
Sapu Lidi = 1.00 bh x 11.150 = 11.150
Cangkul = 1.00 bh x 71.795 = 71.795
Skop = 1.00 bh x 71.795 = 71.795
Pangki = 2.00 bh x 18.500 = 37.000
Rab dan Desain = 1.00 bh x 1.500.000 = 1.500.000
Pamplet = 1.00 bh x 400.000 = 400.000
TOTAL BIAYA PEKERJAAN = 90.968.390

Pages (6)123456 Next

Tidak ada komentar:

Posting Komentar

 
Support : Editing Website | By Sierra | From Original Template Johny
Copyright © 2016. testediteditedit - All Rights Reserved
Template Created by Creating Website Published by Sierra
Proudly powered by Blogger