TAKE OFF SHEET JALAN RABAT BETON_1

★ TAKE OF SHEET PEKERJAAN JALAN RABAT BETON LOKASI DUSUN LAMDAN - GAMPONG LAM HASAN KECAMATAN PEUKAN BADA KABUPATEN ACEH BESAR ★

Note: The column-count property is not supported in Internet Explorer 9 and earlier versions.

GAMBAR
URAIAN
VOLUME
SATUAN
HARGA
,,,,,,,,,,,,GAMBAR PEKERJAAN...............
P1.0 - 38.00 m :
Volume
panjang = 38.00 m
Lebar = 2.00 m
Tinggi = 0.20 m
P 38.00 - 41.60 m :
Volume
panjang = 3.60 m
Lebar = 2.00 m
Tinggi = 0.20 m
P 2. 41.60 - 171.50 m :
Volume
panjang = 129.90 m
Lebar = 3.60 m
Tinggi = 0.20 m
1 M2 PEKERJAAN RABAT BETON
UPAH
Pekerja = 1.093 OH x 77.318.18 = 84.507.30
Tukang = 0.182 OH x 96.095.45 = 17.505.00
Kepala Kelompok = 0.031 OH x 84.100 = 2.565.39
JUMLAH = 104.577.77
BAHAN
Semen = 3.669 Zak x 57.436.00 = 210.708.55
Pasir Pasang = 0.329 m3 x 162.500.00 = 53.391.71
Pasir Urug = 0.051 m3 x 162.500.00 = 8.214.11
Kerikil = 0.446 m3 x 110.455.00 = 49.289.07
JUMLAH = 321.603.43
REKAPITULASI HARGA
UPAH = 104.577.77 x 110.17 M3 = 11.521.124.00
BAHAN = 321.603.43 x 110.17 M3 = 35.430.407.00
PAPAN DELETASI = 77.318.00 x 23.00 Lbr = 1.778.314
Rab / Desain = 1.500.000.00 x 1.00 Bh = 1.500.000.00
Pamplet = 400.000.00 x 1.00 Bh = 400.000.00
JUMLAH = 50.629.845.00

Tidak ada komentar:

Posting Komentar

 
Support : Editing Website | By Sierra | From Original Template Johny
Copyright © 2016. testediteditedit - All Rights Reserved
Template Created by Creating Website Published by Sierra
Proudly powered by Blogger